Apr 11,2016 - Apr 15,2016
Week under review
Apr 11, 2016 – Apr 15, 2016
Iteration Plan
- 11-4-2016 Iteration plan (https://cats-edge.atlassian.net/wiki/display/CATS/11-4-2016+Iteration+Plan )
- The theme of the iteration: Addressing Issues with user permission and validate resolved issues
Product Development Focus
Carryover from previous week
Prioritized support requests
Resolution of support requests
Resolved :
In progress :
- Improvements : (CATS-1237)
SLA percentage for the week
Summary |
|
Total issues this week | 9 |
Total issues due this week | 9 |
Total resolved within the week | 8 |
Total closed within the week | 5 |
Total unresolved | 1 |
|
|
Percent resolved | 88.89% |
Percent closed | 55.56% |
|
|
Total resolved within SLA | 8 |
Total closed within SLA | 5 |
Percent closed within SLA | 55.56% |
Concerns & areas for Improvement
Raised By | Concern | Solution and actions to be taken | JIRA Issue |
The Team | Office setup creates an uncomfortable workplace environment. | Office items should be facilitated: (Ventilation, regular cleaning, Wi-Fi router, water jar, chairs…) |
|
The Team | Power outage: Apr 13,2016 : 8:40am -12:30pm and 2:16 pm -2:45 pm SLA support team is idle for reported time. | Backup generators |
|
The Team | Connection interruption: Apr 11,2016 - 9am-2pm Apr 14,2016 - 11:00 am – 12:09pm | Provision of EVDO |
|
Action Points
Raised by | What is to be done | Why is it needed | Who is responsible (Owner ) | By when (Due Date) | JIRA Issue |
The Team | Office setup creates an uncomfortable workplace environment. | Office items should be facilitated: (Ventilation, regular cleaning, Wi-Fi router, water jar, chairs…) |
| ||
| Power outage: Backup generators should be facilitated | SLA support team is idle for reported time. |
| ||
The Team | Connection interruption: Provision of EVDO
| Lack of updating system and project tracking
|
| ||
Yared Ayalew | No release to date | Provision of testing env for validating and approving resolved items |