Feb 22, 2016 - Mar 4, 2016
Week under review
Feb 22, 2016 – Mar 4, 2016
Iteration Plan
- 22-2-2016 Iteration plan : https://cats-edge.atlassian.net/wiki/display/CATS/22-2-2016+Iteration+Plan
- 29-2-2016 Iteration plan : https://cats-edge.atlassian.net/wiki/display/CATS/29-2-2016+Iteration+Plan
The theme of the iteration : Receiving planning and GRN capture
Product Development Focus
Carry over from previous week
Prioritized support requests
Resolution of support requests
SLA percentage for the week
Summary |
|
---|---|
Total issues this week | 19 |
Total issues due this week | 19 |
Total resolved within the week | 13 |
Total closed within the week | 7 |
Total unresolved | 6 |
|
|
Percent resolved | 68.42% |
Percent closed | 36.84% |
|
|
Total resolved within SLA | 13 |
Total closed within SLA | 7 |
Percent closed within SLA | 36.84% |
Concerns & areas for Improvement
Action Points
Raised by | What is to be done | Why is it needed | Who is responsible (Owner ) | By when (Due Date) | JIRA Issue |
|
|
|
|
|
|
|
|
|
|
|
|