Feb 22, 2016 - Mar 4, 2016

 

       Week under review

                Feb 22, 2016 – Mar 4, 2016

        Iteration Plan

The theme of the iteration : Receiving planning and GRN capture

      Product Development Focus

 

Carry over from previous week

Prioritized support requests

Resolution of support requests

 

   

  SLA percentage for the week

 

Summary 

 

Total issues this week

19

Total issues due this week

19

Total resolved within the week

13

Total closed within the week

7

Total unresolved

6

 

 

Percent resolved

68.42%

Percent closed

36.84%

 

 

Total resolved within  SLA

13

Total closed within SLA

7

Percent closed within SLA

36.84%

 

 

 Concerns & areas for Improvement

 

Raised By

Concern

Solution and actions to be taken

Who is responsible  (Owner )

JIRA Issue

The Team

Git repo setup process , Unable to push changes to the new brunches

Technical support and  instruction document on the suggested “git-flow” approach CM-133 - Getting issue details... STATUS

 

The Team

Office setup creates an uncomfortable workplace environment

Office items should be facilitated :

Ventilation, regular cleaning, Wi-Fi router, water jar, chairs…

Yared Ayalew, Abdulkerim Essa ,            dawit demissie

 

 

CATS PMWe don't have release for second week in a row.Provision and configure testing environment for validating and approving resolved issues. CM-134 - Getting issue details... STATUS   

 

 

Action Points

Raised by

What is to be done

Why is it needed

Who is responsible (Owner )

By when (Due Date)

JIRA

Issue