July 4,2016 -July 8,2016
Week under review
July 4, 2016 – July 8, 2016
Iteration Plan
- 4-7-2016 Iteration plan (4-7-2016 Iteration Plan)
The theme of the iteration: Working on deployment ,test results and UI consistency
Product Development Focus
Prioritized support requests
Resolution of support requests
Resolved:
- 4 Improvements : (CATS-1338, CATS-1339, CATS-1340, CATS-1341 )
- Deployment on QA server and working on test results
Concerns & areas for Improvement
Raised By | Concern | Solution and actions to be taken | JIRA Issue |
The Team | Office setup creates an uncomfortable workplace environment. | Office items should be facilitated: (Better space, Regular cleaning, Wi-Fi router, water jar, network cable…) Move to a different and conducive office environment with close proximity to CATS users. |
|
The Team | Power outage: | Backup generators |
|
Action Points
Raised by | What is to be done | Why is it needed | Who is responsible (Owner ) | By when (Due Date) | JIRA Issue |
The Team | Office setup creates an uncomfortable workplace environment. | Office items should be facilitated: (Better space, Regular cleaning, Wi-Fi router, water jar, network cable…) |
|
| CM-132 - Office items should be facilitated:(Socket divider, Ventilation, regular cleaning, Wi-Fi router, cables, water jar, chairs…)The office is cleaned once a week, it has to be at least 3 days a week with this size of a team. |
The Team | Power outage:
| SLA support team is idle for reported time. |
| CM-135 - Backup power sources whenever the main power goes out |