Aug 22,2016- Aug 26,2016
Week under review
Aug 22, 2016 – Aug 26, 2016
Iteration Plan
- 22-8-2016 Iteration plan (22-8-2016 Iteration Plan)
The theme of the iteration:
- Resolve issues from released validation test result and address all comments from the issues.
Product Development Focus
Prioritized and Resolved support requests
Concerns & areas for Improvement
Raised By | Concern | Solution and actions to be taken | JIRA Issue |
The Team | Office setup creates an uncomfortable workplace environment. | Office items should be facilitated: (Better space, Regular cleaning, Wi-Fi router, water jar, network cable…) Move to a different and conducive office environment with close proximity to CATS users. |
|
The Team | Power outage: | Backup generators |
|
EVDO connection is very slow when used for remote access on QA server. | |||
The Team | Understanding how transaction patterns are implemented and testing was time consuming | A session to discus over all transaction patterns and their current implementations would be great to have. |
Action Points
Raised by | What is to be done | Why is it needed | Who is responsible (Owner ) | By when (Due Date) | JIRA Issue |
The Team | Office setup creates an uncomfortable workplace environment. | Office items should be facilitated: (Better space, Regular cleaning, Wi-Fi router, water jar, network cable…) |
|
| CM-132 - Office items should be facilitated:(Socket divider, Ventilation, regular cleaning, Wi-Fi router, cables, water jar, chairs…)The office is cleaned once a week, it has to be at least 3 days a week with this size of a team. |
The Team | Power outage:
| SLA support team is idle for reported time. |
| CM-135 - Backup power sources whenever the main power goes out |