Sep 19,2016 -Sep 23,2016


Week under review

       Sep 19, 2016 - Sep 23,2016

        Iteration Plan

        The theme of the iteration: 

          • Resolve validation results from the deployment
          • Release validated issues on Production server 
          • Test and validate issues from the internal test column and prepare for upcoming releases.

Product Development Focus


 Prioritized and Resolved support requests

    • Resolved validation results from the deployment and deployed on QA server
    • Test and validate issues from the internal test column and prepare for upcoming release.