Oct 10,2016 – Oct 14,2016
Week under review
Oct 10, 2016 – Oct 14, 2016
Iteration Plan
10-10-2016 Iteration plan (10-10-2016 Iteration Plan )
The theme of the iteration:
- Test the first release issues deployed on the testing environment
- Fix immediately issues that fail business validation (PO Approval)
- Deploy validated issues on Production server if PO validation of all releasable issues is done
- Test issues in internal test using the newly developed testing template and deploy them on the testing environment
Product Development Focus
Carryover from previous week
- Deploy validated issues on Production server if PO validation of all releasable issues is done
Prioritized and Resolved support requests
- Test the first release issues deployed on the testing environment
- Fix immediately issues that fail business validation (PO Approval)
- Test issues in internal test using the newly developed testing template and deploy them on the testing environment