Oct 10,2016 – Oct 14,2016

Week under review

       Oct 10, 2016 – Oct 14, 2016

Iteration Plan

10-10-2016 Iteration plan (10-10-2016 Iteration Plan )

 The theme of the iteration: 

  • Test the first release issues deployed on the testing environment
  • Fix immediately issues that fail business validation (PO Approval)
  • Deploy validated issues on Production server if PO validation of all releasable issues is done 
  • Test issues in internal test using the newly developed testing template and deploy them on the testing environment

Product Development Focus

Carryover from previous week

  • Deploy validated issues on Production server if PO validation of all releasable issues is done

Prioritized and Resolved support requests

  • Test the first release issues deployed on the testing environment
  • Fix immediately issues that fail business validation (PO Approval)
  • Test issues in internal test using the newly developed testing template and deploy them on the testing environment