Nov 14,2016 – Nov 18,2016

Week under review

    Nov 14, 2016 – Nov 18, 2016

Iteration Plan

  • 14-11-2016 Iteration plan ( 14-11-2016 Iteration plan )

  • The theme of the iteration:  Fix issues from the second release (CATS-SLA-R-1.3.2) that fail PO validation, Resolve carry over issues from the fifth release

Product Development Focus 

Carryover from previous week

  • Deploy the second release (CATS-v.1.3.2) on the production server
  • Deploy the third release (CATS-v.1.3.3) on the production server
  • Deploy the fourth release (CATS-v.1.3.4) on the production server
  • Deploy the fifth release (CATS-v.1.3.5) on the production server

Prioritized support requests

Resolution of support requests

Resolved:

SLA percentage for the week

 

Summary

4

Total issues this week

4

Total issues due this week

4

Total resolved within the week

4

Total closed within the week

0

Total unresolved

0



Percent resolved

100%

Percent closed

0%