Dec 12,2016 – Dec 16,2016
Week under review
Dec 12, 2016 – Dec 16, 2016
Iteration Plan
12-12-2016 Iteration plan ( 12-12-2016 Iteration plan)
- The theme of the iteration: Resolve issues that failed PO Validation, Test and validate issues from the internal test column and prepare for upcoming releases, and Conduct UI Improvement
Product Development Focus
Carryover from previous week
- Deploy the third release (CATS-v.1.3.3) on the production server
- Deploy the fourth release (CATS-v.1.3.4) on the production server
- Deploy the fifth release (CATS-v.1.3.5) on the production server
- Deploy the sixth release (CATS-v.1.3.6) on the production server
Prioritized support requests
Resolution of support requests
Resolved:
Summary | 4 |
Total issues this week | 4 |
Total issues due this week | 4 |
Total resolved within the week | 4 |
Total closed within the week | 0 |
Total unresolved | 0 |
Percent resolved | 100% |
Percent closed | 0% |
Concerns & areas for Improvement
Raised By | Concern | Solution and actions to be taken | JIRA Issue |
The Team | Validation process taking a while. Currently, even though we were able to deploy two releases containing 155 issues, we still have the 3rd, 4th, 5th, and 6th weekly releases pending, totally accounting for 51 issues. So, we may need to act on these fast before the release candidates pile up and become a problem. | Speed-up the validation process | |
The Team | Late replies to issue clarification requests on Jira | Prompt response needed on clarification requests on issues acceptance criteria, | |
The Team | SLA developers haven’t been granted a Jira capture permission | Grant all SLA team members Jira capture permission to increase team productivity |