May 9,2016 -May 13,2016
Week under review
May 9, 2016 – May 13, 2016
Iteration Plan
- 9-5-2016 Iteration plan ( 9-5-2016 Iteration Plan )
The theme of the iteration:
- Working on replication issues,test results and change documentation
- Address issues added to the current backlog
Product Development Focus
Support requests
4 Bugs : (CATS-1291,CATS-1293 ,CATS-1285 ,CATS-1260)
Resolution of support requests
Resolved :
Inprogress :CATS-1260 , (This replication issue has been in investigation parallel with the plannings.Pull subscription has been configuration on the Kombolcha server and able to simulate the error. And now we are trying to troubleshoot the error.It may take unknow time to resolve this issue ,will be doing it parallaly)
Concerns & areas for Improvement
Raised By | Concern | Solution and actions to be taken | JIRA Issue |
The Team | Office setup creates an uncomfortable workplace environment. | Office items should be facilitated: (Ventilation, regular cleaning, Wi-Fi router, water jar, chairs…) |
|
Power outage: May 9,2016 : 8:30 am -9:57 am May 10,2016 : 12:21 pm – 1:15 pm May 13,2016 : 4:02 pm – 4:33 pm | SLA support team is idle for reported time. | Backup generators |
|
Connection interruption: May 9,2016 : 8:30 am -9:57 am May 10,2016 : 12:21 pm – 1:15 pm May 13,2016 : 4:02 pm – 4:33 pm May 6,2016 : 11:19am – 1:44 pm
| Lack of updating system and project tracking Difficult to access references and production server | Provision of EVDO |
|
Action Points
Raised by | What is to be done | Why is it needed | Who is responsible (Owner ) | By when (Due Date) | JIRA Issue |
The Team | Office setup creates an uncomfortable workplace environment. | Office items should be facilitated: (Ventilation, regular cleaning, Wi-Fi router, water jar, chairs…) | Yared , Abdulkerim and Dawit
|
|