May 30,2016 - Jun 3,2016
Week under review
May 30, 2016 – June 3, 2016
Iteration Plan
- 30-5-2016 Iteration plan (30-5-2016 Iteration Plan)
The theme of the iteration: Conducting a technical review of CATS to document state of the application to help us identify areas of improvement.
Product Development Focus
No. | Tasks | Activities |
---|---|---|
1 | Database schema ER diagrams and documentation |
|
| ||
| ||
2 | Service layer implementation |
|
| ||
3 | Transaction pattern implementation |
|
| ||
| ||
| ||
4 | Data replication |
|
| ||
| ||
5 | Data security and confidentiality |
|
| ||
6 | Development process |
|
| ||
| ||
7 | User experience and engagement |
|
| ||
| ||
8 | Deployment and operation |
|
| ||
| ||
| ||
9 | User manual and help instruction |
|
| ||
10 | Workflow review |
Concerns & areas for Improvement
Raised By | Concern | Solution and actions to be taken | JIRA Issue |
The Team | Office setup creates an uncomfortable workplace environment. | Office items should be facilitated: ( regular cleaning, Wi-Fi router, water jar, …) |
|
Power outage | SLA support team will be idle | Backup generators |
|
Connection interruption
| Lack of updating system and project tracking Difficult to access references and update documents on wiki | Provision of EVDO |
|
Action Points
Raised by | What is to be done | Why is it needed | Who is responsible (Owner ) | By when (Due Date) | JIRA Issue |
The Team | Office setup creates an uncomfortable workplace environment. | Office items should be facilitated: ( regular cleaning, Wi-Fi router, water jar, ..) | Yared , Abdulkerim and Dawit
|
|
|
Melat Mamo | Investigate jira workflow inconsistency | The modified JIRA workflow is showing inconsistency when using resolution date in filters giving incorrect figures on periodic reports.
|
| CM-140 -Investigate JIRA issue inconsistency OPEN |