Demonstration Timeline
Pre- & Post-demonstration Timeline
GREEN: Product Demonstration
BLUE: Items that are triggered by a RELEASE demonstration
YELLOW: Items that are triggered by a SPRINT demonstration
WHITE: Items that are triggered by both a Sprint AND a Release demonstration
Time relative to Demo Date | Upcoming Demo type | Time | Activity | Who |
---|---|---|---|---|
T minus 1 week* Only in the last sprint of a release, ie. if a new Release is about to start | Release | anytime | Release pre-planning:
| |
T minus 3 days | All | afternoon (2pm) | PO & PM to preview demonstration. Additional preview days at discretion of Yared Ayalew | |
T minus 2-3 days | Release | anytime | Meet with Case-Team leaders who have CATS functionality in Pilot- or Field-test:
| |
T minus 2 days | Release | anytime | Inform key domain experts to attend next sprint planning session | |
T minus 1 day | All | anytime | Reminder email sent to DRMFSS participants | Aaron Holmes |
T- minus 1 day | All | anytime | Ensure items in the Pre-Demonstration Checklist are complete | |
T minus 12 hours | All | afternoon | Final commit to code-branch to be demonstrated | Yared Ayalew |
T minus 1 hour | All | morning | Development team on-site & start set-up | Yared Ayalew |
All | morning (10:00 AM-12:30 PM) | Product Demonstration as per Demonstration Agenda & Checklist Demonstration Discussion as per Demonstration discussion ground rules | Development Team | |
T plus 2 hours | All | afternoon (2pm) | Developers' retrospective | |
T plus 4 hours | Sprint | afternoon (3.30pm) | Sprint planning (not Release planning) | |
T plus 1 day | Release | morning (9:30am - 12:30pm) | Release planning (only when starting a new Release) | Development Team Domain experts |
T plus 1 day | All | morning | Initiate new sprint/release
| Yared Ayalew |
T plus 1 day | All | afternoon | Checkpoint Report preparation | Yared Ayalew |
T plus 2 days | All | afternoon (2pm) |
|